ROADS AND TRAFFIC INFORMATION:

To report the location of potholes, pavement, drainage and a variety of other problems please use the link below:

http://www3.hants.gov.uk/index/transport/roadproblems.htm

You will receive an email directly from HCC when the pothole that you report is repaired.

------------------------------------------------------------------------------------------------------------------------------------------------------------

"As part of the programme of works being undertaken by Operation Resilience we will be undertaking carriageway resurfacing works in Ringwood Road, Burley. These works will extend from the fire station to the Burley County Primary School. Pre-resurfacing civil works are programmed to start on Monday 19th September 2016 and are expected to last for 5 days, during which time Ringwood Road and Pound Lane will be subject to temporary 2-way and 3-way traffic signals. The signals will operate 24 hours a day for the duration of the works.

The carriageway resurfacing works are programmed to start on Monday 26th September 2016 and are expected to last for 5 nights. In order to undertake the resurfacing works safely it will be necessary to close the road from 22:00 to 06:00hrs.

Information signs advising road users of the works will be erected. A letter will be sent to local residents and an email will be sent to Burley Parish Council and New Forest District Council to advise them accordingly."

Hampshire County Highways, HCC 7/9/16

-------------------------------------------------------------------------------------------------------------------------------------------------------------

"As part of the programme of works being undertaken by Operation Resilience we will be undertaking footway and drainage works in Ringwood Road, Burley. These works will extend from The Odd Spot access to The Burley Stores on the north side of the road and from Howards Close to the Magpies Nest on the south side. The works are programmed to start Monday 18 January 2016 and are expected to last for 8 weeks, during which time Ringwood Road and Pound Lane will be subject to temporary 3-way traffic signals. The signals will operate 24 hours a day for the duration of the works." HCC 07/01/2016

-------------------------------------------------------------------------------------------------------------------------------------------------------------

Details of  proposed waiting restriction in Burley adobe icon Waiting restriction [295kb] adobe icon Map [66kb]

-------------------------------------------------------------------------------------------------------------------------------------------------------------

Click here for information on A31 resurfacing and carriageway closures adobe icon A31 resurfacing [58kb]

Diversion map adobe icon Diversion map [248kb]

---------------------------------------------------------------------------------------------------------------------------------------------------------------

A338 road works adobe icon A338 road works - 2 [2Mb]

There will be two weeks of night closures in November to carry out survey work in preparation for phases two, three and four. 

The A338 will be closed between the Ashley Heath Roundabout on the A31 and the Cooper Dean Roundabout on the A3060:

From 8pm Monday 2 November until 6am Tuesday

From 8pm Tuesday 3 November until 6am Wednesday

From 8pm Wednesday 4 November until 6am Thursday

From 8pm Thursday 5 November until 6am Friday

From 8pm Friday 6 November until 6am Saturday

 

The week commencing Monday 9 November is provisionally booked for night closures in case of bad weather in the first week or the need for further survey work.

A week of night closures is also due the week starting Monday 7 December. 

 

Please click here for further information on the roadworks including bus services and Royal Bournemouth Hospital appointments http://news.dorsetforyou.com/bournemouth-spur-road/

From 6 September for two weeks, there will be day time and night time lane closures on the northbound and southbound carriageways, there will also be some overnight closures. During these two weeks work will concentrate on removing any remaining trees or vegetation obstructing the work, installing traffic management, speed cameras and CCTV and resurfacing works around Blackwater.

From the 21 September until Christmas, the southbound carriageway will be reconstructed between Blackwater Junction and the QinetiQ access, with a 40mph contraflow on the northbound carriageway.

In the New Year work will focus on the northern end of the scheme, with the reconstruction of the roughly one-mile stretch between Ashley Heath Roundabout and the QinetiQ entrance. Work will start on the southbound side, with traffic remaining in the northbound contraflow, and then the works area and contraflow will swap sides - with traffic switching over to the newly built southern carriageway to allow the northbound one-mile section to be reconstructed.

There will also be speed restrictions on the A31 in this area during this phase of work.

From March until the end of May, the northbound carriageway will be reconstructed with the contraflow traffic on the newly built southbound side.

Throughout the work there may be times where additional overnight closures are required for surfacing work and to rearrange traffic management.

Further information from Dorset Highways:

We've now got more detail for you about the 'phasing' (or order) of our work.

We'll be moving anti-clockwise around the Bournemouth Spur Road, between Ashley Heath Roundabout and Blackwater Junction, with the reconstruction starting on the main southbound stretch of road.

6 September - two weeks of day time and night time lane closures on the northbound and southbound carriageways, with some overnight closures. We'll be removing any remaining trees and vegetation obstructing the work, installing traffic management, speed cameras and CCTV and doing resurfacing works around Blackwater.

Phase 1
21 September to Christmas - southbound carriageway reconstructed between Blackwater Junction and the QinetiQ access, with a 40mph contraflow on the northbound carriageway.

Phase 2 and 3
3 January to March - reconstruction of the roughly one-mile stretch between Ashley Heath Roundabout and the QinetiQ entrance. Work will start on the southbound side, with traffic remaining in the northbound contraflow, and then the works area and contraflow will swap sides. There will also be speed restrictions on the A31 during this phase of work.

Phase 4
March to end of May - the northbound carriageway will be reconstructed with the contraflow traffic on the newly built southbound side.

Throughout the work there may be times where additional overnight closures are required for surfacing work and to rearrange traffic management.